Project case study

Stratford International, London, UK

Aviation and rail

Supporting international rail travel

  • Increased departure capacity by 30%
  • More efficient security and passport zones
  • Increased retail area by 100%
  • Improved passenger flows within the station
Client

HighSpeed1

Value
£6 million
Partners

Morgan Sindall plc

Working from limited base build information the design team engaged with the client and stakeholders to drive the delivery of goals and efficiencies required for successful station operation, not only immediately but for the long term.

As an existing building within the Olympic site the programme had to be coordinated through a number of other contractors on site to make sure works were not impacted. This was achieved through close liaison, communication and assessment of construction logistics and project boundaries with domestic operator Southeastern and their fit-out contractor.

Want to know more?

Download our detailed case study for Stratford International.