River Derwent Temporary Bridge, Workington, UK

  • Fast construction through engagement with partners
  • Accelerated opening to re-link local communities
  • Early design commitment ensured delivery to programme
  • Fully demountable and recyclable components.
Client

Cumbria County Council

Partners

Morgan Sindall plc

Following the destruction of several bridges during the catastrophic floods across Cumbria in November 2009 we were part of the
award-winning team
tasked with reuniting the Workington community through emergency procurement, design and delivery of the project in just 10 weeks.

Working closely with the client, principal designer and contractor we undertook in depth analysis of different solutions and recommended a bridge type based upon technical performance and cost.

Completed with the full exposure of national media attention and so inevitably required high levels of programme and technical certainty.

Award winning

British Construction Industry Award 2010
Winner of “Best Small Civil Engineering Project”

Ground Engineering Awards 2011
Finalist in “Geotechnical or Geoenvironmental UK project up to £1m”